BELFAST BICYCLE NETWORK: A New time schedule?

Looking at the figures revealed this week by John Mulgrew of the Belfast Telegraph. We've done some quick calculations.

Here’s how the total £100 Million budget for the Belfast Bicycle Network breaks down, according to DfI's 10 year project delivery plan.

SCHEDULE YEAR BUDGET
Year 1 2021–22 £1M
Year 2 2022–23 £3M
Year 3 (current)
2023–24 £5M
Year 4 2024–25 £7M
Year 5 2025–26 £9M
Year 6 2026–27 £11M
Year 7 2027–28 £13M
Year 8 2028–29 £15M
Year 9 2029–30 £17M
Year 10 2030–31 £19M
£100M



DfI confirmed to @newsmulg the spend for 23–24 = £0.5M.

That’s 10% of what was pledged for 2023-24.

No idea what previous years’ spend was – let’s give benefit of doubt and assume it was the same.

Let's also assume this is the same going forward.

A quick calculation shows the timescale to complete the Belfast Bicycle Network has slipped from 10 years…

to around 200 years.

As we’ve said over the years – the Belfast Bicycle Network isn't happening and there's nothing you, your councillor, MLA or Minister can do about it.